T-type Multi-branch Drilling Technology    

Oil production increased by 6-12 times;

Recovery efficiency of reservoir increased more than 15%

The maxium production of single well after T drilling is 3980ton.

The single well production on off-shore after T drilling is 1100bbls



How long does it take?

2025-04-19

Under normal conditions, T-type well takes:


No.

Working program

Working-hours (h)

Remarks

1

Depth correction

3

working hour is difference for different layer;

2

Azimuth adjusting

3

Working time is different according to the azimuth equipment;

3

Whipstock hanging

0.5


4

Casing milling

3

The length of windows milling is 0.6-0.8m; The compound milling cone is fit for high-strength steel casing,such as P110、N80;

5

Building-up operation

3

The length of building-up hole is 4-6 meters;

6

Horizontal stage drilling

40

The average RPM of horizontal stage is 3m/h; T-type hole 90m, the purely drilling time maybe 30 hours.